FDOT Treasure Coast Traffic Report: January 9 through January 13

[ad_1]

MARTIN, ST. LUCIE & INDIAN RIVER COUNTIES – Monday January 9, 2023: Treasure Coast traffic will be affected this week by ongoing construction projects and maintenance work in Martin, St. Lucie and Indian River counties, Florida Department of Transportation (FDOT) officials report. Please note, any full road, ramp or bridge closures have been highlighted below.

For around-the-clock, real-time, I-95 traffic information, visit www.fl511.com. For updated lane closure information, please refer to www.d4fdot.com. Follow us on Twitter and Instagram @ MyFDOT_SEFL and on Facebook @MyFDOTSEFL.

CONSTRUCTION PROJECTS

MARTIN COUNTY

(Hobe Sound, Palm City, City of Stuart, Stuart, Jensen Beach, Jupiter Island, Port Salerno, Rio, Indiantown, Tequesta, Town of Sewall’s Point)

1. State Road 714/SW Martin Highway Widening Project
Description: This 1.127-mile widening project began on Aug. 6, 2021. Project improvements include widening SR 714/SW Martin Highway from a two-lane undivided rural roadway to a four-lane divided urban roadway, widening the bridge over Florida’s Turnpike, constructing seven-foot buffered bike lanes and six-foot sidewalks on both sides of the roadway, and installing signing, signalization, and lighting upgrades.
Cost/Completion: $21.3 million. Completion is expected in fall 2024.
Traffic Impact:

  • The eastbound and westbound shoulders on SR 714/SW Martin Highway from SW Martin Downs Boulevard to SW Citrus Boulevard are closed through mid-2024 to facilitate widening activities. Cyclists and motorists should share the road.
  • Advance Notice: Beginning Tuesday, Jan. 17, southbound Florida’s Turnpike between Becker Road (Exit 138) in St. Lucie County and SR 714/Martin Highway (Exit 133) in Martin County, will be closed to traffic overnight, 10:30 p.m. until 5:30 a.m., through Thursday night, Jan. 19 for bridge widening work.
  • Detour Information:
  • Westbound Becker Road traffic will be detoured via the I-95 southbound entrance ramp to SR-706/Indiantown Road.
  • The southbound Florida’s Turnpike entrance ramp from SR-714/Martin Highway will not be impacted and will remain accessible during this operation. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

2. State Road 5/U.S. Highway 1 Resurfacing Project
Description: This 1.426-mile resurfacing project from SR 732/NW Jensen Beach Boulevard to the Martin County/St. Lucie County line began on Monday, May 2, 2022. Project improvements include milling and resurfacing the existing roadway; adding bicycle lanes within the project limits: 5-feet wide from SR 732/NW Jensen Beach Boulevard to NW Sunset Boulevard and 7-feet wide from NW Sunset Boulevard to the Martin County/St. Lucie County Line; upgrading curb ramps to meet American with Disabilities Act (ADA) standards; and upgrading pedestrian signals, intersection lighting, pavement markings, and signing to current standards.
Cost/Completion: $3,071,783.35. Completion is expected spring 2023.
Traffic Impact:

  • One lane in each direction on SR 5/U.S. 1 from NW Jensen Beach Boulevard to the Martin County/St. Lucie County line will be closed Monday, Jan. 9 through Friday, Jan. 13, from 9 a.m. to 4 p.m., for concrete replacement work. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

3. State Road 76/Kanner Highway Resurfacing Project
Description: This 1.4-mile resurfacing project from north of Cabana Point Circle to SR 5/U.S. 1 in the City of Stuart will began on Monday, July 25, 2022. Project improvements include milling and resurfacing the existing roadway; some minor widening will occur along northbound and southbound SR 76/Kanner Highway; upgrading crosswalks and curb ramps to meet Americans with Disabilities Act (ADA) standards; installing sidewalks, signage and pavement markings; upgrading pedestrian lighting at two signalized intersections at SR 714/Monterey Road and SR 5/U.S. 1; and, upgrading or restoring drainage pipes and replacing sections of the City of Stuart’s watermain at various locations.
Cost/Completion: $5,064,094.62. Completion is expected summer 2023.
Traffic Impact:

  • One southbound outside lane of SR 76/Kanner Highway from the Monterey Road intersection to SR 5/U.S. 1 may be closed around the clock through Tuesday, Feb. 28, 2023, for drainage, utility, sidewalk, and lighting work. 
  • One northbound outside lane of SR 76/Kanner Highway from the parking entrance to Water’s Edge Dermatology south of Monterrey Intersection to SE Lonita Street will be closed from 8 a.m. to 4 p.m. as needed, starting on Wednesday, Jan. 4 to Wednesday, Feb. 8, for lighting, signalization, and site restoration work.
  • Two northbound outside lanes of SR 76/Kanner Highway from the Monterey Road intersection to SR 5/U.S. 1 will be closed nightly from 8 p.m. to 6:30 a.m. through Sunday, Jan. 18, for lighting work and milling and resurfacing the roadway.  
  • Two southbound lanes of SR 76/Kanner Highway from the intersection of Monterey Road to SR 5/U.S. 1 will be closed nightly Monday through Friday, through Tuesday Feb. 28, from 8 p.m. to 6:30 a.m. for drainage, utility, sidewalk, and lighting work. 
  • One westbound lane of SR 714/SW Monterey Road from the Monterey Shopping Plaza driveway to the European Kitchen and Bath driveway may be closed from 8 a.m. to 4 p.m., as needed, through Wednesday, February 8, 2023, for lighting, foundation work.
  • One northbound lane of SR 76/S Kanner Highway from SR 5/U.S. 1 to Seacoast Bank Court will be closed from 8 a.m. to 6:30 p.m. as needed, through Wednesday, Feb. 8, for lighting, foundation work.
  • One eastbound lane of SR 5/U.S. 1 from the Citgo Gas Station in front of the Twin Plaza Shopping Center to the first driveway entrance to Bank of America Financial Center will be closed from 8 a.m. to 4 p.m. as needed, through Wednesday, Feb. 8, for lighting work.
  • One northbound lane of SR 76/Kanner Highway from SW Cabana Point Circle to Seacoast Bank just north of SR 5/U.S. 1 will be closed nightly Monday through Friday, through Sunday, Jan. 18, from 8 p.m. to 6:30 a.m. for milling and resurfacing work.
  • Two northbound outside lanes of SR-76/Kanner Highway from the Monterey Road intersection to SR 5/U.S. 1 will be closed Sunday through Thursday, through Monday, Jan. 16, from 8:30 p.m. to 6 a.m. for lighting work and milling and resurfacing the roadway.
  • Advanced Notice: Beginning at 8 p.m., Friday, Jan. 20, southbound SR 76/Kanner Highway at the intersection of SR 5/U.S. 1, will be closed around-the-clock through approximately 6:30 a.m., Monday, Jan. 23, for watermain and roadway construction. Friday, Jan. 27 through Monday, Jan. 30 will be used as contingency dates if needed.
  • Detour Information:
  • Southbound SR 5/U.S. 1 traffic will be detoured via SR 714/Monterey Road to SR 76/Kanner Highway.
  • Northbound SR 5/U.S. 1 traffic will be detoured via SR 714/Monterey Road to SR 76/Kanner Highway. Please see flyer attached.
  • Advanced Notice: Beginning at 6 p.m., Tuesday, Jan. 17, the entrance to Poppleton Creek at southbound SR 76/Kanner Highway, will be closed around-the-clock through approximately 10 a.m., Tuesday, Jan. 24, for watermain work. Tuesday, Jan. 24 through Wednesday, Feb. 1 will be used as contingency dates if needed.
  • Detour Information:
  • Northbound SR 76/Kanner Highway traffic will be detoured via SR 714/Monterey Road and SW Palm City Road to the Poppleton Creek entrance at SW Riverview Street.
  • Southbound SR 76/Kanner Highway traffic will be detoured via SR 5/U.S. 1 and SW Palm City Road to the Poppleton Creek entrance at SW Riverview Street.
  • Southbound SR 5/U.S. 1 traffic will be detoured via SW Palm City Road to the Poppleton Creek entrance at SW Riverview Street. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

4. State Road 9/I-95 Weigh In Motion (WIM) Stations Highway Lighting Improvements Project
Description:
Cost/Completion: $1,074,789. Completion is expected spring 2023.
Traffic Impact:

  • The northbound WIM station located just north of the Indiantown Road interchange is open.
  • The southbound WIM station located just south of the Becker Road interchange is closed around-the-clock through Saturday, June 3, 2023, pending weather and unforeseen circumstances, to remove the existing highway lighting features and install new highway lighting. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 

ST. LUCIE COUNTY

(City of Port St. Lucie, Port St. Lucie, White City, City of Fort Pierce, Fort Pierce, Okeechobee, St. Lucie West, Tradition)

5. Kings Highway Widening Project, from South of State Road 70 to North of the I-95 Overpass
Description: Kings Highway / State Road 713 is being widened from south of State Road 70 to north of the I-95 overpass in the City of Ft. Pierce and unincorporated St. Lucie County. The improvements on this 3.417-mile project include: reconstructing the existing two-lane undivided Kings Highway into a newly constructed four‐lane divided roadway, relocating Canal No. 40 and Canal No. 32E to accommodate widening to the west, realigning Kings Highway at the intersection with Okeechobee Road which will improve the existing connection with the Turnpike, replacing existing culverts/swales and installing a closed drainage system and retention ponds, installing a new highway lighting system, and upgrading signalization with vehicle detection devices and ITS cameras.
Cost/Completion: $45.2 million. Completion is expected in spring 2023.
Traffic Impact:

  • The speed limit on Kings Highway from south of Okeechobee Road / State Road 70 to north of the I-95 overpass has been temporarily reduced from 50 MPH to 40 MPH. This speed limit reduction will be in place through the end of the project.
  • One lane in either direction of Kings Highway may be intermittently closed Monday through Thursday from 9 a.m. to 4 p.m. through spring 2023 for roadway work. Two-way traffic will be maintained by a flag crew. During this time, intermittent side street closures may occur, maintaining two-way traffic at all times.
  • Northbound Kings Highway at the Orange Avenue intersection is reduced to one lane in each direction through spring 2023, temporarily removing the designated turning lanes, to facilitate roadway reconstruction.
  • Northbound and southbound traffic on Kings Highway from just north of Crossroads Parkway to south of Orange Avenue is shifted to the east on the newly constructed road to facilitate the reconstruction of Kings Highway.
  • Traffic on Kings Highway between the State Road 70/Okeechobee Road intersection and Pruitt Research Center Road was shifted to the newly constructed southbound lanes, to allow for widening operations and new northbound lane construction through spring 2023. One lane of traffic will remain open in each direction, separated by double yellow lines (no passing zone).
  • Northbound and southbound traffic on Kings Highway between north of Picos Road and Orange Avenue was shifted to the new northbound pavement, to allow for widening operations and southbound lane construction through spring 2023. One lane of traffic will be open in each direction separated by double yellow lines (no passing zone).
  • Northbound and southbound traffic on Kings Highway just south of Orange Avenue was shifted to the new southbound pavement until Access Road, where northbound traffic will shift back onto the existing northbound pavement to allow for widening operations and lane construction through spring 2023. One lane of traffic will remain open in each direction, separated by double yellow lines (no passing zone.
  • One lane in either direction of Kings Highway from Okeechobee Road to north of the I-95 bridge will be closed intermittently Monday, Jan. 9 through Thursday, Jan. 12, from 6 a.m. to 4 p.m. for roadway work. Traffic will be maintained by a flag crew.
  • One lane in either direction of Kings Highway from Okeechobee Road to north of the I-95 bridge will be closed nightly Sunday, Jan. 8 through Thursday, Jan. 12, from 8 p.m. to 6 a.m. for maintenance of traffic control work.
  • One lane in either direction of Orange Avenue from just west of Kings Highway to just east of Kings Highway will be closed nightly Sunday, Jan. 8 through Thursday, Jan. 12 from 8 p.m. to 6 a.m. for drainage work. Traffic will be maintained by a flag crew.
  • Advanced Notice: Kings Highway, between Pruitt Research Road and Crossroads Parkway, will be closed nightly, 8 p.m. to 6 a.m., Wednesday, Jan. 18 and Thursday, Jan. 19, for traffic shift operations. Jan. 22 through Jan. 26 will be used as contingency nights if needed.
  • Detour Information:
  • Traffic will be detoured via Graham Road, Jenkins Road, Okeechobee Road, and Crossroads Parkway.
  • Once the traffic shift is completed, one outside lane in each direction of Kings Highway will be open on the new roadway.
  • Advanced Notice: Orange Avenue at Kings Highway and the northbound and southbound off-ramps to westbound Orange Avenue, will be closed nightly, 8 p.m. to 6 a.m., Wednesday, Jan. 18 and Thursday, Jan. 19, for traffic shift operations. Sunday, Jan. 22, through Friday, Jan. 27 will be used as contingency nights if needed.
  • Detour Information:
  • Orange Avenue at Kings Highway and the northbound and southbound I-95 off-ramps to westbound Orange Avenue, will be closed nightly, 8 p.m. to 6 a.m., Sunday, Jan. 8, through Thursday, Jan. 12, for roadway work. Jan. 17 and Jan. 18 will be used as contingency dates if needed.
  • Westbound Orange Avenue traffic will be detoured via S Jenkins Road, Graham Road, Kings Highway, Picos Road, and S Rock Road to Orange Avenue.
  • Eastbound Orange Avenue traffic will be detoured via Rock Road, Picos Road, Kings Highway, Graham Road, and S Jenkins Road to Orange Avenue.
  • I-95 to westbound Orange Avenue traffic will be detoured to the eastbound Orange Avenue off-ramps and directed to follow detour signage.
  • Once the traffic shift is completed, one outside lane of traffic in each direction of Kings Highway will be open on the new roadway.
  • Detour Information:
  • Westbound Orange Avenue traffic will be detoured via S Jenkins Road, Graham Road, Kings Highway, Picos Road, and S Rock Road to Orange Avenue.
  • Eastbound Orange Avenue traffic will be detoured via Rock Road, Picos Road, Kings Highway, Graham Road, and S Jenkins Road to Orange Avenue.
  • I-95 to westbound Orange Avenue traffic will be detoured to the eastbound Orange Avenue off-ramps and directed to follow detour signage. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

6. SW Port St. Lucie Boulevard Widening Project, from South of SW Alcantarra Boulevard to South of SW Darwin Boulevard
Description: Construction on this 0.713-mile widening project began on Thursday, Jan. 27, 2022, in the City of Port St. Lucie. The City of Port St. Lucie, as Project Sponsor, requested the Florida Department of Transportation (FDOT), District Four design and construct this project through application to the St. Lucie Transportation Planning Organization and City of Port St. Lucie Resolution 18-R42. Project improvements include widening SW Port St. Lucie Boulevard from a two-lane undivided roadway to a four-lane divided roadway, installing three new signalized intersections with mast arms at SW Alcantarra Boulevard, SW Tulip Boulevard, and SW Tunis Boulevard, adding a right turn lane on SW Port St. Lucie Boulevard’s north approach to SW Alcantarra Boulevard, constructing an 18’ wide raised median with curb and gutter, upgrading crosswalks and curb ramps to meet Americans with Disabilities Act (ADA) standards, constructing 8’-10’ wide sidewalks on both sides of SW Port St. Lucie Boulevard for pedestrian and bicycle use, and 6’ wide sidewalks on side streets, installing a new closed drainage system, signing, pavement markings, signalization, and lighting upgrades, and landscaping for the median including trees, irrigation and stamped concrete.
Cost/Completion: $11,570,179. Completion is expected summer 2024.
Traffic Impact:
One lane in each direction of SW Port St. Lucie Boulevard between SW Squirrel Avenue and SW Darwin Boulevard will be closed Monday, Jan. 9 through Friday, Jan. 13, from 8 a.m. to 3 p.m. to install drainage structures, storm pipe, line stops and final connections, and perform pressure testing and chlorination work. Flagging operations will be in place to direct traffic. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.
City of Port St. Lucie project/adjacent to project corridor:
The Port St. Lucie Boulevard South Project Segment 3, managed by the City of Port St. Lucie, is reconstructing approximately 0.7 miles of the existing four-lane roadway from SW Gatlin Boulevard to SW Darwin Boulevard and a portion of SW Darwin Boulevard through Winter 2023.
Traffic Impact:

  • Speed limit lowered to 30 mph for the duration of the construction project.
  • Closure of existing median openings at both SW Yale Street and SW Cairo Avenue.

One northbound through lane will be eliminated on SW Port St. Lucie Boulevard north of SW Aurelia Avenue to Gatlin Boulevard, leaving one through lane and one dedicated left turn lane onto westbound Gatlin Boulevard. For more information about the City of Port St. Lucie’s Segment 3 Project, please contact Beth Zsoka, Project Public Information Specialist at 772-871-5176.
7. St. Lucie West Boulevard Widening Project, from Commerce Center Drive to Peacock Boulevard
Description: This 1.814-mile widening project began on Monday, January 24, 2022, in the City of Port St. Lucie. The City of Port St. Lucie, as Project Sponsor, requested the Florida Department of Transportation (FDOT), District Four design and construct this project through application to the St. Lucie Transportation Planning Organization and City of Port St. Lucie Resolution 20-R75. Project improvements include constructing a new 3-lane eastbound bridge over I-95, separated 10-feet from the existing bridge; widening St. Lucie West Boulevard to accommodate two (2) eastbound and westbound travel lanes, with a third eastbound lane between the I-95 southbound and northbound ramps, two (2) eastbound left turn lanes at the I-95 northbound on ramp, two (2) westbound right turn lanes at the I-95 northbound on ramp; reconstructing/widening the I-95 ramps; connecting the existing St. Lucie West Boulevard roadway to the new eastbound bridge from the east and west directions; constructing 7-foot buffered bike lanes/paved shoulder and 5-foot to 6-foot wide sidewalks on both sides of the roadway; constructing a 22-foot to 40-foot lane-line to lane-line curbed median with curb and gutter; installing fencing retrofits on the north side of the existing bridge, and new railing on the eastbound bridge; and, installing new traffic signals with enhanced synchronization and timing at I-95 ramps.
Cost/Completion: $15,518,729. Completion is expected fall 2023.
Traffic Impact:

  • The eastbound lane of St. Lucie West Boulevard from the I-95 northbound off-ramp intersection to Peacock Boulevard was shifted 3-feet to the north to facilitate roadway construction through spring 2023.
  • Eastbound St. Lucie West Boulevard to southbound I-95 traffic is shifted to the newly paved temporary on-ramp through Jan. 2023 to facilitate roadway construction.
  • Eastbound and westbound traffic on St. Lucie West Boulevard just west of I-95 near the southbound on and off-ramps is shifted to the north through Jan. 2023.
  • The eastbound lane of St. Lucie West Boulevard just west of the I-95 northbound on and off-ramps will be shifted to the south through Jan. 2023.
  • The bike lane and shoulder along eastbound St. Lucie West Boulevard are closed through Mar. 2023. The asphalt pathway along westbound St. Lucie West Boulevard will be open and can be used by bicycles.
  • Traffic on the northbound I-95 on-ramp is shifted to the outside (right) lane through Feb. 2023 to facilitate roadway construction operations.
  • Traffic on the northbound I-95 off-ramp is shifted to the inside (left) lane to facilitate roadway construction operations through Jan. 2023. The dedicated right turn lane is still in place and operational.
  • Traffic on the southbound I-95 off-ramp is shifted to the inside (left) lane eliminating the dedicated right turn lane onto westbound St. Lucie West Boulevard to facilitate roadway construction operations through Jan. 2023.
  • Intermittent shoulder closures may occur Monday through Friday, from 7 a.m. to 5 p.m. for road work at the following locations:
  • One lane in either direction of St. Lucie West Boulevard between Champions Way and SW Peacock Boulevard may be intermittently closed nightly Monday through Friday, from 10 p.m. to 6 a.m. for roadway work. A flagging operation will be in place to help direct traffic.
  • One northbound and southbound lane of I-95 may be intermittently closed from just north and south of the St. Lucie West Boulevard overpass Monday through Friday, from 7 a.m. to 5 p.m., for bridge work and deliveries.
  • One northbound and southbound lane of I-95 may be intermittently closed from just north and south of the St. Lucie West Boulevard overpass Monday through Friday, from 8 p.m. to 6 a.m., for bridge work and material deliveries. No more than one lane will be closed at a time in either direction of I-95.
  • Two southbound and northbound lanes of I-95 from one mile south to one mile north of the St. Lucie West Boulevard overpass may be intermittently closed Monday through Friday, from 10 p.m. to 5 a.m., for bridge work.
  • Two northbound lanes of I-95 from one mile south to one mile north of the St. Lucie West Boulevard overpass will be closed nightly from 9 p.m. to 5 a.m., Sunday, Jan. 8 through Sunday, Jan. 15, for bridge construction activities.
  • The southbound I-95 off-ramp to eastbound and westbound St. Lucie West Boulevard may be closed nightly Monday, Jan. 9, through Thursday, Jan. 12, from 11 p.m. to 5 a.m., for milling and resurfacing of the southbound off-ramp. Traffic will be detoured via the I-95 southbound exit to Crosstown Parkway (Exit 120), Crosstown Parkway, and northbound I-95 to St. Lucie West Boulevard. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 
  • Northbound and southbound I-95 mainline from just north and south of the St. Lucie West Boulevard overpass
  • All I-95 on and off-ramps at St. Lucie West Boulevard
  • Eastbound and westbound St. Lucie West Boulevard from Champions Way to SW Peacock Boulevard

8. State Road 716/Port St. Lucie Boulevard Over Long Creek & N. Fork of the St. Lucie River Bridge Rehabilitation Project
Description: This 0.3-mile bridge rehabilitation project began on Saturday, March 19, 2022, in the City of Port St. Lucie. Project improvements include removing the existing deteriorated east and west seawalls (concrete caps and steel sheet piles) and replacing with rubble riprap slope protection and repairing the existing spalls in the concrete piles and concrete beams at various locations.
Cost/Completion: $1,436,682. Completion is expected winter 2022.
Traffic Impact:

  • All lanes are open. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

9. State Road 9/I-95 Northbound and Southbound Off-Ramps at Gatlin Boulevard Roadway Improvements Project
Description: This 1.4-mile roadway improvements project began on Friday, June 10, 2022. Project improvements include widening southbound I-95 to provide a 12-foot auxiliary lane and a 12-foot shoulder (10-feet paved); widening I-95 southbound Gatlin Boulevard off-ramp for the addition of a right-turn lane and a left-turn lane; widening the inside of the I-95 northbound Gatlin Boulevard off-ramp to provide three (3) left-turn lanes; widening eastbound and westbound Gatlin Boulevard to provide three 15-foot left-turn lanes; modifying drainage to an open system with dry ponds; installing one cantilever sign structure at the southbound I-95 off-ramp; and adding new signing and pavement markings.
Cost/Completion: $4,627,785.77. Completion is anticipated fall 2023.
Traffic Impact:

  • The outside or inside ramp lane of the northbound I-95 to eastbound and westbound Gatlin Boulevard exit ramps may be closed from 9 a.m. to 4 p.m., Monday through Friday, through Jan. 2023, for roadway work.
  • The outside or inside ramp lane of the northbound I-95 to eastbound and westbound Gatlin Boulevard exit ramps may be closed from 9 a.m. to 4 p.m., Monday through Friday, Tuesday, Jan. 3 through Tuesday, Jan. 31, 2023, for roadway work.
  • The outside shoulder of the southbound I-95 to eastbound and westbound Gatlin Boulevard exit ramp is closed around-the-clock through March 2023 to facilitate roadway work.
  • One westbound outside lane of Gatlin Boulevard from just west of the I-95 northbound on-ramp entrance to just east of the overpass is closed around-the-clock through Jan. 2023, for roadway work.
  • One lane in each direction of Gatlin Boulevard from just east and west of the northbound and southbound I-95 off-ramps at Gatlin Boulevard may be closed from 7 a.m. to 5 p.m., Monday through Friday, through Jan. 2023, for clearing and grubbing, and sidewalk work. During this time, sections of the sidewalks will be closed, and pedestrian detours will be in place.
  • One lane in each direction of Gatlin Boulevard from just east and west of the northbound and southbound I-95 off-ramps at Gatlin Boulevard may be closed from 7 a.m. to 5 p.m., Monday through Friday, Tuesday, Jan. 3 through Tuesday, Jan. 31, 2023, for clearing and grubbing, and sidewalk work. During this time, sections of the sidewalks will be closed, and pedestrian detours will be in place.
  • Southbound I-95 to the eastbound/westbound exit ramp to Gatlin Boulevard may be closed nightly, 9 p.m. until 6 a.m., Sunday night, Jan. 8, through Friday morning, Jan. 13, for barrier wall construction. During the closure, motorists will be detoured via southbound I-95 to the Crosstown Parkway exit ramp (Exit 120), then turn right onto Crosstown Parkway, turn left onto SW Village Parkway to Gatlin Boulevard. Signage will be in place to assist motorists. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

10. State Road 9/I-95 Northbound and Southbound Off-Ramps at Midway Road Improvements Project
Description: This roadway improvements project began on Nov. 10, 2022. The project improvements consist of adding a second left-turn lane to both the SR 9/I-95 northbound and southbound off-ramps at Midway Road (Exit 126); widening and repaving the existing SR 9/I-95 off-ramps; upgrading traffic signals with new mast arm poles and improving signalization timing and alignment; implementing Wrong Way Driving Countermeasure Systems; and upgrading existing highway lighting along with implementation of new signing and pavement markings.
Cost/Completion: $2.6 million. Completion is anticipated summer 2023.
Traffic Impact:

  • The left turn lane on the I-95 northbound off-ramp onto westbound Midway Road is closed around-the clock through March 2023 to facilitate roadway construction activities. During this closure, motorists will be detoured via the I-95 northbound off-ramp to eastbound Midway Road and make a U-Turn at LTC Parkway to head west on Midway Road.
  • The left turn lane on the I-95 southbound off-ramp onto eastbound Midway Road is closed around-the-clock through March 2023 to facilitate roadway construction activities. During this closure, motorists will be detoured the I-95 southbound off-ramp to westbound Midway Road and make a U-Turn at Gordy Extended to head east on Midway Road.
  • The inside shoulder on the I-95 northbound off-ramp to Midway Road is closed around-the-clock through March 2023 to facilitate roadway construction activities.
  • The inside shoulder on the I-95 southbound off-ramp to Midway Road is closed around-the-clock through March 2023 to facilitate roadway construction activities. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

INDIAN RIVER COUNTY

(City of Vero Beach, Vero Beach, Indian River Shores, Sebastian, Wabasso, Wabasso Beach, City of Fellsmere)

11.   SR A1A and SR 5/US 1 Roadway Improvements Project
Description: This roadway improvements project is anticipated began August 26, 2022.The SR A1A from south of Jasmine Lane to north of SR 60/Beachland Boulevard project improvements consist of repaving and restriping the existing asphalt pavement; widening the roadway to accommodate a 7-foot buffered bicycle lane; constructing a 6-foot sidewalk on the east side (northbound direction); upgrading drainage, signage and pavement markings; upgrading existing curb ramps to meet Americans with Disabilities Act (ADA) standards; adding two signalized pedestrian mid-block crossings at Iris Lane and Dahlia Lane; and, upgrading pedestrian signal and lighting at the intersection of SR A1A and SR 60/Beachland Boulevard. SR A1A and SR 5/US 1 turn lanes project improvements consist of constructing a southbound right turn lane at the intersection of SR 5/US 1 and 8th Street; extending the southbound right turn lane at the intersections of SR A1A and the 17th Street Causeway and SR A1A and SR 60/Beachland Boulevard; and upgrading existing drainage.
Cost/Completion: $5.6 million. Completion is anticipated fall 2023.
Traffic Impact:

  • The northbound shoulder of SR A1A will be closed around-the-clock through Tuesday, Jan. 31, for drainage and other construction activity work.
  • The northbound lane of SR A1A between 17th Street and SR 60/Beachland Boulevard will be intermittently closed from 9 a.m. to 3:30 p.m., Monday through Friday, through Tuesday, Jan. 31, for deliveries. Flagging operations will be in place. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

MAINTENANCE, UTILITY, PERMIT & ADDITIONAL AGENCY PROJECTS

MARTIN COUNTY

(Hobe Sound, Palm City, City of Stuart, Stuart, Jensen Beach, Jupiter Island, Port Salerno, Port Mayaca, Rio, Indiantown, Tequesta, Town of Sewall’s Point)

CITY OF STUART:
Eastbound and westbound SE Ocean Boulevard between SE Monterey Road and SE Georgia Avenue, in the City of Stuart, 9 a.m. to 3:30 p.m., through Saturday, Jan. 7, 1 of 4 lanes intermittently closed, for directional bore work. Motorists are encouraged to follow detours, exercise caution, and expect delays. For more information, please contact Susan Kingsley at 772-288-5459.
Northbound and southbound NW Dixie Highway over the Old Roosevelt Bridge, in the City of Stuart, 9 a.m. to 4 p.m., Monday, Jan. 23 through Friday, Jan. 27, 1 of 2 lanes closed, for routine maintenance. For more information, please contact Guillermo Canedo, Communications Manager, FDOT District Four at 954-777-4302.

HOBE SOUND:
Northbound U.S. 1 between SE Village Road and SE Seabranch Boulevard, in Hobe Sound, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes may be closed, for FP&L utility pole installation and wiring operations. For more information, please contact Rafael Ureña at 772-882-5084. 

TEQUESTA:
Northbound and southbound U.S. 1 between SE Jupiter Inlet Way and Coconut Road, in Tequesta, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes closed, for utility work. For more information, please contact Rafael Ureña at 772-882-5084.

I-95:
Northbound I-95 between 500-feet south to 200-feet north of bridge over Bridge Road, in Hobe Sound, around-the-clock, until repairs are completed, the outside shoulder closed, for bridge beam repair work. For more information, please contact Guillermo Canedo, Communications Manager, FDOT District Four at 954-777-4302.

BRIGHTLINE:

Jensen Beach – Riverview Drive. Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit Riverview Drive. For more information, please contact Katie Mitzner at 407-502-3587.
Jensen Beach – Skyline Drive. Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit Skyline Drive. For more information, please contact Katie Mitzner at 407-502-3587.
Jensen Beach – NE Jensen Beach Boulevard. Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit NE Jensen Beach Boulevard. For more information, please contact Katie Mitzner at 407-502-3587.
Jensen Beach – NE Dixie Highway. Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit NE Dixie Highway. For more information, please contact Katie Mitzner at 407-502-3587.
Stuart – Alice Street. Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit NW Alice Street. For more information, please contact Katie Mitzner at 407-502-3587.
Stuart – NW Fern Street. Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit NW Fern Street. For more information, please contact Katie Mitzner at 407-502-3587.
Stuart – West of SE Dixie Highway/A1A between SE Decker Avenue and SE Monterey Road. Daytime southbound shoulder closures for concrete pouring, Monday to Friday, 7 a.m. to 3 p.m. For more information, please contact Katie Mitzner at 407-502-3587.
Stuart – Southbound A1A from south of SE Cove Road to south of SE Alicia Street. Continuous shoulder closure through Q1 2023. For more information, please contact Katie Mitzner at 407-502-3587.
High Speed Testing up to speeds of 110 mph. Daytime testing, 7 a.m. to 7 p.m., Friday, Jan. 6 through Monday, Jan. 23. Flaggers and law enforcement will be present at the following railroad crossings where trains will operate at high speeds.
St. Lucie County

  • Walton Road
  • Riverview Drive

Martin County

  • County Line Road
  • Skyline Drive (CR 722)
  • Pitchford Landing
  • For more information, please contact Katie Mitzner at 407-502-3587.

ST. LUCIE COUNTY

(City of Port St. Lucie, Port St. Lucie, White City, City of Fort Pierce, Fort Pierce, Okeechobee, St. Lucie West, Tradition)

CITY OF PORT ST. LUCIE:
Westbound SW Port St. Lucie Boulevard between SW Airoso Boulevard and SW Trenton Boulevard, in the City of Port St. Lucie, around-the-clock beginning at 9 a.m. Monday, Jan. 9 through 4 p.m., Friday, Jan. 13, 1 right lane of 3 lanes closed, for milling and resurface work. Westbound SW Port St. Lucie Boulevard traffic will be detoured to SW Trenton Lane to SW Crescent Avenue. For more information, please contact Christian Vargas at 321-369-8924.
Eastbound and westbound Port St. Lucie Boulevard between SE Carmin and SE Exchange Street, in the City of Port St. Lucie, 9 p.m. to 4:30 a.m., Thursday, Jan. 12, 1 outside lane of 6 lanes closed, for mast arm removal at 1616 Port St. Lucie Boulevard. Police officers will be on site to assist motorists. For more information, please contact Robert McIntosh at 772-577-9764.

FORT PIERCE:
Northbound and southbound A1A between Anglefish Drive and Compass Cove Place, in Fort Pierce, 9 p.m. to 4 a.m., Monday, Jan. 9 through Friday, Jan. 13, 2 of 3 lanes closed, for utility work. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound U.S. 1 between Goforth Boulevard and Tropical Isle Way, in Fort Pierce, 9 p.m. to 4 a.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 3 lanes closed, for installation and/or replacement of FPL poles. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound U.S. 1 between Goforth Boulevard and Tropical Isle Way, in Fort Pierce, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 3 lanes closed, for installation and/or replacement of FPL poles. For more information, please contact Rafael Ureña at 772-882-5084.
Eastbound and westbound SR A1A (North Bridge), in Fort Pierce, 9 a.m. to 4 p.m., Tuesday, Jan. 10 through Friday, Jan. 13, 1 of 2 lanes closed, for routine maintenance. For more information, please contact Guillermo Canedo, Communications Manager, FDOT District Four at 954-777-4302.
Northbound U.S. 1 between Avenue H and Avenue O, in Fort Pierce, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes closed, for water main replacement and directional boring work. The work being performed in sections through the project corridor. Only one section will be closed at a time. For more information, please contact John Biggs at 772-466-1600 ext. 3474.

PORT ST. LUCIE:
Westbound SW Port St. Lucie Boulevard between SW Airoso Boulevard to SW Trenton Boulevard, in Port St. Lucie, around-the-clock beginning at 9 a.m. Monday, Jan. 9 through 4 p.m., Friday, Jan. 13, 1 right lane closed, for milling and resurface work. Westbound SW Port St. Lucie Boulevard traffic will be detoured to SW Trenton Lane to SW Crescent Avenue. For more information, please contact Christian Vargas at 321-369-8924.

I-95:
Southbound I-95 between just north and south of the bridge over the St. Lucie River, in Port St. Lucie, 9:30 a.m. to 3:30 p.m., Wednesday, Jan. 18, 1 of 3 lanes closed, for routine maintenance. For more information, please contact Guillermo Canedo, Communications Manager, FDOT District Four at 954-777-4302.

BRIGHTLINE:
High Speed Testing up to speeds of 110 mph. Daytime testing, 7 a.m. to 7 p.m., Friday, Jan. 6 through Monday, Jan. 23. Flaggers and law enforcement will be present at the following railroad crossings where trains will operate at high speeds.
St. Lucie County

  • Walton Road
  • Riverview Drive

Martin County

  • County Line Road
  • Skyline Drive (CR 722)
  • Pitchford Landing
  • For more information, please contact Katie Mitzner at 407-502-3587.

INDIAN RIVER COUNTY

(City of Vero Beach, Vero Beach, Indian River Shores, Sebastian, Wabasso, Wabasso Beach, Orchid Island, City of Fellsmere)

VERO BEACH:
Northbound and southbound SR 5 between Grand Harbor Boulevard and 57th Street, in Vero Beach, 9 a.m. to 4 p.m., Monday through Friday, through Friday, Jan. 27, 1 of 2 lanes closed, for utility pole operations. For more information, please contact Rafael Ureña at 772-882-5084.
Eastbound SR 60 between 26th Avenue and 27th Avenue, in Vero Beach, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 3 lanes closed, for utility pole operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound and southbound SR A1A between Sandpiper Lane and Jasmine Lane, in Vero Beach, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes closed with possible lane shifts, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound and southbound SR A1A between Beachcomber Lane and John Island Drive, in Vero Beach, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes may be intermittently closed with possible lane shifts or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound and southbound SR A1A between Beachcomber Lane and John Island Drive, in Vero Beach, 9 p.m. to 6 a.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes may be intermittently closed with possible lane shifts or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound and southbound Indian River Boulevard between Royal Palm Boulevard and 20th Street, in Vero Beach, 9 p.m. to 6 a.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes closed, for FP&L utility pole installation and wring operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound and southbound Indian River Boulevard between Royal Palm Boulevard and 20th Street, in Vero Beach, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes closed, for FP&L utility pole installation and wring operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound and southbound SR 5 between 21st Street SE and Grove Isle Circle, in Vero Beach, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes closed, for utility pole operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound and southbound SR 5 between Grand Harbor Boulevard and 57th Street, in Vero Beach, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes closed, for utility pole operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound and southbound SR A1A between Jingle Trail and McLarty Treasure Museum, in Vero Beach, 9 p.m. to 6 a.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes may be intermittently closed with possible lane shifts or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.
Northbound U.S. 1 between 61st Place and 57th Street, in Vero Beach, 9 a.m. to 4 p.m., Monday, Jan. 9 through Friday, Jan. 13, 1 of 2 lanes closed, for utility pole operations. For more information, please contact Rafael Ureña at 772-882-5084.
Eastbound and westbound SR 60 between 800’ west of 43rd Avenue and 50’ east of 38th Avenue, in Vero Beach, 9 p.m. to 6 a.m., Sunday through Thursday nights beginning Tuesday, Jan. 3 through Tuesday, Jan. 31, up to 3 of 6 lanes closed, for asphalt paving. For more information, please contact Colton Griffin at 772-529-0788.
Southbound 43rd Avenue between 9th Place and 6th Street, in Vero Beach, 9:30 a.m. to 3:30 p.m., Monday, Jan. 9 through Tuesday, Jan. 10, the right shoulder and partial lane of 2 lanes closed, for utility work. For more information, please contact Pete Rolan at 772-318-9560.
Westbound 8th Street between 43 Avenue and 49th Avenue, in Vero Beach, 9:30 a.m. to 3:30 p.m., Wednesday, Jan. 11 through Thursday, Jan. 12, the right shoulder and partial lane of 2 lanes closed, for utility work. For more information, please contact Pete Rolan at 772-318-9560.
Eastbound 20th Street east of 9th Avenue, in Vero Beach, 9 a.m. to 4 p.m., Monday, Jan. 9, 1 of 3 lanes closed, for utility work in manhole located in sidewalk. For more information, please contact Jermaine McClendon at 772-342 6878 or the technician on-site Shawn Ramirez at 772-332-0745.

BRIGHTLINE:
Sebastian – Railroad Crossing at Main Street. Full road closure, 7 a.m., Tuesday, Jan. 3 to 7 p.m., Friday, Jan. 20.
Detour Information

  • Eastbound Main St. traffic will be directed to travel south on Powerline Road to Sebastian Blvd., travel east on Sebastian Boulevard to U.S. 1 and travel north on U.S. 1 to Main Street.
  • Westbound Main Street traffic will be directed to travel south on U.S. 1 to Sebastian Boulevard, travel west on Sebastian Boulevard to Powerline Road and travel north on Powerline Road to Main Street. For more information, please contact Katie Mitzner at 407-502-3587. 

Vero Beach – Railroad Crossing at 8th Street / Glendale Road. Full road closure, 7 a.m., Monday, Jan. 9 to 7 p.m., Wednesday, Jan. 25.
Detour Information

  • Eastbound 8th Street traffic will be directed to travel south on Old Dixie Highway to 4th Street, travel east on 4th Street to U.S. 1 and travel north on U.S. 1 to 8th Street.
  • Westbound 8th Street traffic will be directed to travel south on U.S. 1 to 4th Street, travel west on 4th Street to Old Dixie Highway and travel north on Old Dixie Highway to 8th Street. For more information, please contact Katie Mitzner at 407-502-3587. 

Vero Beach – Railroad Crossing at U.S. 1 and Aviation Boulevard (32nd Street). Southbound U.S. 1 lane closure, 9 a.m. to 4 p.m. Saturday, Jan. 7, Sunday, Jan. 8, Saturday, Jan. 14 and Sunday, Jan. 15. For more information, please contact Katie Mitzner at 407-502-3587. 

www.fdot.gov